For the first time in India, a 210 MW power unit was commissioned in 27 months setting an International Record & Desein is proud to be associated in providing Consultancy on various packages and furnishing engineering & construction documentation to achieve the record 
      

 
           
           
RAICHUR THERMAL POWER STATION   
EXTN-UNITS 5 & 6 EACH OF 210 MW CAPACITY 

   
Desein was involved in providing Consultancy to Karnataka Power Corporation Ltd. for extension Unit # 5&6. This project was funded by various financial Institutions, Banks & Major equipment supplier, as such timely completion of the Project was a key factor in this job since delay in achieving every milestone was linked with liquidated damages. 
  
The Unit No.5 was scheduled to be commissioned and to be taken over for commercial operation in 156 weeks (i.e. 36 months) and Unit No.6 in 182 weeks (i.e. 42 months) from zero date which was reckoned from 2nd September, 1996. 
  
Commissioning & Commercial operation of each Unit was later preponed by six (6) months as Main Equipment Supplier agreed to prepone his supplies. Desein took the challenge in providing engineering & construction documentation to meet the preponed schedule which resulted in achieving the target even before the preponed Target Schedule as shown below: 

Zero Date for start of the Project.................. 2-9-96
      
Activity

Unit # 5

Unit # 6  

Mile Stone Schedule Actual Schedule Actual
Boiler Erection Start 30-06-97

   18-06-97

28-12-97 24-12-97
Drum Lifting    26-01-98     01-11-97 27-07-98 30-04-98
Boiler Light Up 25-01-99 19-11-98 26-07-99 20-05-98
Synchronization
& Commissioning
24-05-99 30-01-99
(27 months)
22-11-99 22-07-99
  
As indicated above preponed target date of 30 months was in actual achieved in a record time of 27 months setting International Utility Record in Commissioning of 210 MW Coal fired thermal power unit. 

   
STEAM GENERATOR & AUXILIARIES 

Steam Generator & other Auxiliaries installed at Raichur was convensional  
   two pass, radiant reheat, natural circulation water cooled welded wall 
   furnance, single drum, semi outdoor type unit to use as coal as principal
   fuel.

Firing system equipped with High Energy Arc ignitor system & tilting
   nozzle type corner fired coal burners connected to a master control lever
   which actuate all nozzle to the same degree simultaneously as a unit, for
   stablizing flame as per load requirement for automatic/ remote operation. 
  
  
TURBINE GENERATOR & AUXILIARIES
   
Fully hydrogen cooled generator with brushless excitation system excitor
   used as advance technology in the TG unit installed. 
  
Two pass type Condensers installed with stainless steel tube in air zone &
   cupro-nickled tubes in water zone for longer life of tubes. 
  
HP heater and LP heater were provided of vertical construction for compact
   installation and effective drainage. 
 
 
INSTRUMENTATION & CONTROL 

With increase in Unit size of plants, the number of points required to be monitored as well as the number and complexity of the control loops has increased rapidly. This has necessitated an increase in the instruments and fast dynamic displays to be provided on the control panel for operator's interactions which has further resulted in miniaturisation of instruments, computerised data acquisition system, microprocessor based distributed Digital Control system for close loop and open loop control, sequence of event recording with millisecond resolution, auto start of various drives with group control system. 

In order to meet with the above objectives, Control Instrumentation (C&I) package for Raichur Unit 5&6 was provided. Salient features provided under C&I package are described as follows: 
  
Control System Equipment 
   

Computerised Digital Distributed Control and management information system (DDCMIS) Centum-XL have been provided for modulating control, protection and sequential Control functions of plant through redundant I/O cards, redundant 32 bit process and state of art Man-machine interface modules. The system is based on multi loop/ multi function controller concept. 

Complete automation has been provided by integrating open loop and close loop control functions and by providing operator guidance message on CRT, complete automatic start-up, loop up, shut down operation under cold, warm and hot status of the plant in a prescribed manner thus avoiding human errors. For sequence of operations stand above SER system of RIS have been provided. 

Turbo Generator supplier provided control system Procontrol P-B for integral Turbine Control for ATRS, TSI etc. similarly for integral Steam Generator control for burner management system Procontrol P-B have been provided. In addition various fields instruments of latest design have been used for this project.
          
   

       
                                   


Home | Company Profile | Tie Ups | Services | Performance | International Projects