Desein's track record and its contributions for achieving speedy
execution of projects should be a major factor in a client's
choice of a consultant for their project.
 

Desein's services in the following projects towards the achievement of
record completion schedules was well recognised by the client and
all other concerned agencies.

           
Raichur unit #5 (210 MW) in 27 months 
           
Kothagudem unit # 9 (250 MW) in 31 months

    

Raichur TPS of Karnataka Power Corporation Limited (KPCL)
     

Capactiy   210MW

No. of Units  2

Boiler Manufacturer

Bharat Heavy Electricals Limited
 
TG Manufacturer
Bharat Heavy Electricals Limited

KPCL will be able to save around Rs. 2000 Million in the implementation of the 210MW Raichur Thermal expansion project because of the fast implementation of the project in a record 14 weeks ahead of schedule.     

                            

 

  

Kothagudem TPS, Stage - V, 
Unit# 9 of Andhra Pradesh State 

Electricity Board (APSEB)

Capacity   250 MW

No. of Units  2
 
Boiler Manufacturer
Bharat Heavy Electricals Limited


TG Manufacturer
Bharat Heavy Electricals Limited

Kothagudem-V (Unit# 9), a 250 MW coal fired unit that was set-up in 31 months was a record.Kothagudem-V is providing more power to the people of Andhra Pradesh, boosting industrial output, helping farmers to produce more, lighting up many more homes and bringing a smile on many more faces.
        

 

     

   

                                   